Steel Plant


In our steel plant we have an Electric Arc Furnace with 75 tons of liquid steel capacity and power of 72 MVA transformer.

We use scrap as raw material and produce 700.000 tons of prime concast steel billets per year.

The liquid steel produced in the electric arc furnace is taken to the ladle furnace with 10 MVA capacity and alloying elements are added for producing steel meeting the production standards.

The liquid steel is carried to the Continuous Casting Machine with 6 channels by means of liquid steel casting crane, then cast to water cooled copper molds and turned into billets.